Menu Close

Penalties, damages, the law and you

A recent High Court case is a timely reminder to review your commercial contracts, particularly if your business uses standard form contracts.

Penalties, damages, the law and you

In the unfortunate event you are faced with a breach of contract by another party, it’s important to know that the damages clause in your contracts enables you to recover as much of the loss suffered as possible.

Damages clauses have traditionally been drafted conservatively so as to avoid law against “penalties”, but a recent High Court decision has changed the legal landscape for damages and paved the way for greater scope of costs and other legitimate business interests to be calculated in damages clauses.

What is a penalty clause?

Most contracts contain provisions as to liquidated damages: a specified sum of money payable by a party in breach of the contract to the innocent party. A builder who fails to complete a project on time, a supplier who does not meet delivery or a breach of a confidentiality clause are a few common examples which may attract liquidated damages.

Importantly, any clause setting out liquidated damages must be a genuine pre-estimate of loss suffered by the innocent party.

The law against penalties provides that where such a clause is “out of proportion” to the potential damage, or “extravagant and unconscionable”, it will be considered a “penalty” and therefore void and unenforceable.

The case

The recent case of Paciocco v Australia and New Zealand Banking Corporation [2016] HCA 28 concerned a claim that the late-payment fees, overdraft fees and dishonour fees charged by ANZ on various banking facilities were excessive and out of proportion to the loss suffered by ANZ and were therefore invalid penalty clauses.

The disputed fees were between $20 and $35 each.

On appeal from decisions in both the Federal Court and Full Court, the High Court ruled that although the fees were not an estimate of “loss”, they were calculated having regard to the “legitimate business interests” of ANZ.

The court held that when considered against the value of an individual credit card, the fees might have appeared excessive. However, late payments resulted in flow-on consequences and gave rise to additional costs, including regulatory capital requirements, operational costs associated with debt recovery and provisioning costs associated with the risk of outstanding debt.

The court held that these costs increased due to customers’ failure to meet their contractual obligations and pay their credit card bills on time.

What does this mean for your contracts?

Damages clauses have traditionally been drafted with caution so as not to trigger the law against penalties. The High Court however has taken a broad view and determined that damages are not limited to loss resulting directly from a breach of the contract, but may include a wide range of legitimate business interests.

The Paciocco case has reinforced the court’s increasing support of freedom to contract and is a timely reminder to review your commercial contracts, particularly if your business uses standard form contracts. You should be carefully considering all legitimate business interests and costs arising from a breach of your contracts, including regulatory compliance and operational costs.

Leave a Reply